Project Update




Several communication mechanisms are in place to keep the community informed about ongoing activities at Sasol's Lake Charles Chemicals Project. SasolTEXT, a text message notification system, delivers information directly to your mobile device. Please visit the SasolTEXT page for sign-up instructions.

Ethane Cracker & Derivatives Project Update

  • Progressed to 98 percent overall project completion (as of June 30, 2019)
  • Construction progress is at 94 percent completion
  • Commissioning activities underway
Milestones Achieved
  • Ethylene Oxide/Ethylene Glycol (EO/EG) Unit reaches beneficial operation in June 2019
  • Linear Low Density Polyethylene Unit reaches beneficial operation in February 2019
  • LCCP achieves first steam
  • Sasol sets 317-foot ethylene oxide wash tower--tallest component at Louisiana mega project site
  • Sasol sets 1,380 ton ethylene oxide reactor--heaviest component at Louisiana mega project site
  • Rotating traffic signals installed--first of their kind in Louisiana
  • 16 Louisiana businesses strengthened and widened 2.36 miles of roadway in 192,700 man-hours for the heavy haul route

To learn more about these and other milestone achievements, please visit our project photos and media page.

Last update: August 02, 2019


   

 